Epuron commenced development activities at the site in late 2008, with the establishment of the first wind monitoring tower on site. Since then, Epuron has installed a number of additional masts and begun to prepare a concept for the site, culminating in the lodgement of the Project Application with the Department of Planning
Due to the improving market conditions, Epuron has now commenced development of this proposal in earnest.
| Status | Timing | Update |
| Target | 2014-15 | Wind farm construction/operation |
| Target | 2013 | Grid connection consent achieved |
| Target | 2013 | Planning consent achieved |
| Target | Q3 2012 | Environmental Assessment lodged |
| Target | Q2 2012 | Specialist studies complete |
| Target | Q1 2012 | Project Consultation Plan |
| Complete | Dec 2011 | Newsletter #3 released |
| Underway | Nov 2011 | Biodiversity studies commenced |
| Complete | Jan 2011 | Planning Application submitted |
| Complete | Jun 2010 | Newsletter #2 released |
| Complete | Dec 2009 | Newsletter #1 released |
| Complete | Jun 2009 | 3rd wind monitoring mast installed |
| Complete | Mar 2009 | 2nd wind monitoring mast installed |
| Complete | Nov 2008 | 1st wind monitoring mast installed |
| Complete | 2008-10 | Initial land agreements secured |