Wind farm development takes time

Epuron commenced development activities at the site in late 2008, with the establishment of the first wind monitoring tower on site. Since then, Epuron has installed a number of additional masts and begun to prepare a concept for the site, culminating in the lodgement of the Project Application with the Department of Planning

Due to the improving market conditions, Epuron has now commenced development of this proposal in earnest.

Status Timing Update
Target 2014-15 Wind farm construction/operation
Target 2013 Grid connection consent achieved
Target 2013 Planning consent achieved
Target Q3 2012 Environmental Assessment lodged
Target Q2 2012 Specialist studies complete
Target Q1 2012 Project Consultation Plan
Complete Dec 2011 Newsletter #3 released
Underway Nov 2011 Biodiversity studies commenced
Complete Jan 2011 Planning Application submitted
Complete Jun 2010 Newsletter #2 released
Complete Dec 2009 Newsletter #1 released
Complete Jun 2009 3rd wind monitoring mast installed
Complete Mar 2009 2nd wind monitoring mast installed
Complete Nov 2008 1st wind monitoring mast installed
Complete 2008-10 Initial land agreements secured
View the project documents Jump to Epuron Projects

Latest Project News

  • 14 Mar 12 |
    NSW Wind Farm Guidelines Response

    Epuron today submitted its response to the NSW Government’s draft Wind Farm Planning Guidelines. Epuron fully supports the focus on…

  • 13 Mar 12 |
    Community Consultation Framework

    Epuron has today released its Community Consultation Framework.  This Framework has been developed to further enhance Epuron’s consultation processes, and…

  • 7 Dec 11 |
    Rye Park Update #3

    Our biodiversity consultants have just completed a spring-summer field survey across the development envelope for the project site in line with the DGRs. The biodiversity survey was comprehensive…

  • 14 Nov 11 |
    Epuron returns to local ownership

    Epuron was today acquired by Fulcrum Energy after a buy-out by Epuron’s existing management.  As a result, Epuron returns to…

  • 1 Jun 10 |
    Rye Park Update #2

    The Rye Park project area is located across the Boorowa LGA, Upper Lachlan Shire LGA and the Yass Valley LGA,…